In view of the problem of concrete crack of rock anchor beam in the period of construction,the paper introduces the main loads which could produce adverse stress.According to the measured value of inhomogeneous displacement of rock face,the elastic finite element analysis is been done by ANSYS,and the results show that the larger tensile stresses which are caused by inhomogeneous displacement of rock face are located in the concrete near free face.The simulation of temperature field and stress field has been done,and the analysis of occurrence and development of temperature and stress in middle section shows that main reason of concrete crack is the temperature distribution and its ongoing change.
[1]Lien R,Kristiansen J,Pran L S.Suspended Supportfor Crane Rails in Norwegian Underground Power-houses[J].International Water Power and DamConstruction,1990,42(4):48-50.
[2]涂志军,崔巍.小湾水电站地下厂房岩锚梁现场试验研究[J].岩土力学,2007,28(6):1 139-1 144.
[3]徐跃之,肖汉江,陕亮.三峡电站地下厂房岩锚梁温度应力控制措施探讨[J].水利水电科技进展,2008(3):50-53.
[4]张建均.锦屏二级水电站地下厂房岩锚梁施工[J].水利水电技术,2008,39(11):49-51.
[5]师锋民,李文华.溪洛渡左岸地下电站岩锚梁开挖施工[J].人民长江,2008,39(14):96-98.
[6]门红,李贵祥,张同港,等.蒲石河抽水蓄能电站地下厂房宕描梁开挖施工[J].水利水电施工,2008(3):32-34.
[7]金丰年,翁杰,苏新军.地下工程那个中岩锚吊车梁若干问题的探讨[J].岩石力学与工程学报,2003,22(Z1):2 187-2 191.
[8]王俤剀,彭琦,汤荣,等.地下厂房岩锚梁裂缝成因分析[J].岩石力学与工程学报,2007,26(10):2 125-2 129.
[9]朱伯芳.大体积混凝土温度应力与温度控制[M].北京:中国电力出版社,1998.
Basic Information:
China Classification Code:TV544
Citation Information:
[1]WEI Yongsheng LI Daoshan(Guoan Construction Group Corporation Limited of Henan Province,Luoyang 471023,China).Analysis on the Cause of Cracks of Rock Anchor Beam during the Construction Period[J].Water Resources and Power,2010,28(01):93-96.
2010-01-25
2010-01-25